Maximo Essentials V7.1 - Implementer’s Guide
��
There is a management buy-in for this project.
��
A dedicated single point of contact and project manager is appointed from the 
customer to manage interactions with end users
��
Historic data migration can be done by implementation team but data 
cleansing and scrubbing needs to be owned by the customer.
3.3  Task Break Down
The standard phases of a Maximo Essentials implementation project are:
��
Phase 1: Requirement Gathering and Analysis
��
Phase 2: Solution Design
��
Phase 3: Deployment
��
Phase 4: Testing and Go-Live
��
Phase 5: Support
The key activities in each of the phases are explained in the following sections.
Phase 1: Requirement Gathering and Analysis
Roles Involved: Project Manager, Business Analyst, Solution Architect
Key Activities:
��
Understand current business processes for
– Maintenance Management, 
– Procurement, 
– Inventory Management 
– Asset Management
��
Document pain areas with existing business processes
��
Demo the vanilla product 
��
Understand and document the end goal and vision of the customer
��
Document ‘To-Be’ business processes for each of the functions mentioned 
above
��
Analyze the points of integration
��
Analyze the current data sources
��
Creation of a SRS (Software Requirements Specification) document
Phase 2: Solution Design
Roles Involved: Project Manager, Business Analyst, Solution Architect