test sys-link 
8
Parameters
test sys-link
test sys-link UUCSSpp [channel # ] [current | faulted]
[short | long][repeat # | clear] [schedule]
The test sys-link command will validate the existence of the specified link and 
run diagnostic tests on the hardware path that comprises the system link. If the 
“current” or “faulted” option is specified, tests are run on all hardware objects 
that comprise the specified link. If “current” or “faulted” is not specified, only the 
end-to-end sys-link connection will be tested.
The hardware path that comprises a system link consists of up to 21 hardware 
components that affect the behavior of the link. The number of components of a 
given system link hardware path depends on the system configuration and type 
of system link. The following links are examples of system links: Expansion 
Archangel Links (EAL), Indirect Neighbor Links (INL), Processor Gate Control 
links (PGC), PRI signaling links (PRI), System Access Port links (SAP), X.25 
adjunct links (X25).
Parameters
Examples
test sys-link 2e0201 current l schedule
test sys-link 2e0201 faulted r 10
test sys-link 1c1701 channel 3 r 10
long
Both long and short sequences run Test #417. If Stratum 3 synchronization is 
administered, an additional non-destructive test (#649) is run by the long 
sequence.
UUCSSpp
The location of the port associated with the system link.
channel 
number
The processor channel (1 to 128) associated with an X.25 adjunct link to 
be tested.
current
This specifies testing of the current hardware path of the system link.
faulted
This specifies testing of the hardware path of the system link as it was 
constituted when a fault last caused the link to go down. For more 
information, se