Page 10-290
CARR-POW (Carrier Port Power Unit) for DC-Powered Systems 
10
5. Move the locking slide on the replacement power unit to the extreme left 
position and open the locking lever.
6. Insert the power unit into the carrier until some resistance is felt.
7. Lift the locking lever upward until it latches.
8. Move the locking lever slide on the power unit to the extreme right 
position.
9. Connect the power cord.
10. If this is a 645B power unit, set the power switch to ON.
Hardware Error Log Entries and Test to Clear 
Values
a. Where P is an appropriate port network number taken for the Port field of 
the Error Log.
b. Run the Power Unit Query Test (#127) first using the 
test environment P r 
2
 command. Then, if a carrier must be recycled to clear the CARR-POW 
alarm, use the 
recycle carrier PC
 command to run the Power Unit 
Recycle Test (#126). The Power Unit Recycle Test (#126) is not included 
in either the long or Short Test Sequences.
!
WARNING:
The Power Unit Recycle Test (#126) is destructive. For more 
information, refer to the description of this test.
1.
Run the Short Test Sequence first. If all tests pass, run the Long Test Sequence. Refer to the 
appropriate test description and follow the recommended procedures.
Carrier Port Power Unit Error Log Entries
Error 
Type
Aux 
Data
Associated Test
Alarm 
Level
On/Off 
Board
Test to Clear Value
0
1
0
Any
Any
Any
test environment P sh r 1
1(a)(b)
0 or 1
Power Unit Query 
Test (#127)
MAJOR
ON
test environment P r 2