Layer 2 Status Test (#647)
The Layer 2 Status Test checks the layer 2 status of the ISDN-PRI Signaling 
Channel (D-channel). This test will fail if there is a hardware failure or a facility 
problem, or if the primary and secondary ISDN-PRI D-channels are not 
administered correctly.
The Primary and Secondary Signaling Link Hardware tests (test 636 and 639) 
and the Remote Layer 3 Query test (test 637) will detect most problems caused 
by hardware failures or incorrect administration. However, the Layer 3 test (test 
637) cannot detect end-to-end transmission problems with the Standby 
D-channel since Layer 3 messages are not sent on the standby channel.
For G3r, the SYS-LINK Maintenance Object reports Layer 2 ISDN-PRI D-channel 
problems and for G3i/s/vs, the PI-LINK Maintenance Object reports Layer 2 
ISDN-PRI D-channel problems (if the D-channel is connected to the Processor 
Interface circuit pack). However, the PI-LINK Maintenance Object does not 
monitor the Layer 2 status of the ISDN-PRI D-channel when the D-channel is 
connected to the Packet Control circuit pack for the ISDN-PRI over PACCON 
4
FAIL
There is a problem with the Processor Interface Link. No DS1 ISDN 
Trunk (B-channel) or Wideband PRI Endpoint calls can be made 
until the problem is resolved.
1. Display the Communication-Interface Links Form via the 
display communication-interface
 command to determine 
which link is down (find the one that matches the DS1 Interface 
circuit pack on which this ISDN-PRI Signaling Link Port resides) 
and then refer to the PI-LINK Processor Interface Link 
Maintenance documentation.
8
FAIL
There is a problem with the DS1/UDS1 Interface circuit pack or the 
ISDN-PRI Secondary Signaling channel (D-channel). No ISDN 
Trunk (B-channel) or Wideband PRI Endpoint calls can be made 
until the problem is resolved.
1. Refer to the DS1/UDS1 circuit pack and the ISDN-PRI Signaling 
channel (ISDN-LNK/ISDN-PLK) Maintenance documentation.
PASS
The basic physical connectivity of the Signaling Group’s Secondary 
D-channel is intact and functional. Try this test repeatedly to ensure 
the link is up and to uncover any transitory problems.
Table 10-226.
TEST #639 Secondary Signaling Link Hardware Check  — 
Continued
Error 
Code
Test 
Result
Description/ Recommendation