Lucent Technologies R5SI Manual Do Utilizador

Página de 2643
DEFINITY Enterprise Communications Server Release 5
Maintenance and Test for R5vs/si  
555-230-123  
Issue 1
April 1997
Maintenance Object Repair Procedures 
Page 10-1061
PI-LINK (Processor Interface Link) 
10
7. Try to isolate the problem in the link if hardware is at fault. Test the link via 
the 
test link lnk-no long
 system technician command.
a. If Test #182 fails three times, replace the TN765 circuit pack. Refer 
to 
b. If Test #182 passes and Test #183 fails, replace the TN754 or 
TN784 Digital Line or the TN722 or TN767 DS1 Interface circuit 
pack, whichever is used in the link. If Test #183 still fails, replace 
the TN765 PI-BD. Refer to 
8. If the preceding tests pass:
Check the physical transmission link:
a. Are all the circuit packs physically installed?
b. Are the cables still connected throughout?
c. Check DS1-BD error section for possible connectivity problems if 
DS1-BD is used in link connection.
d. Check CSU options.
9. Finally, restart the Processor Interface circuit pack via 
reset interface 
PCS
. This resets the circuit pack and restarts ALL the links on it.
System Technician-Demanded Tests: 
Descriptions and Error Codes
Always investigate tests in the order presented in the table below when 
inspecting errors in the system. By clearing error codes associated with the 
PI 
Loop Around Test
, for example, you may also clear errors generated from other 
tests in the testing sequence. REMINDER: The command line entry to test the 
PI-LINK MO is: 
test link lnk-no (s or l)
.
Order of Investigation
Short Test 
Sequence
Long Test 
Sequence
D/ND
1
Processor Interface Loop Around Test (#182)
X
D
TDM Loop Around Test (#183)
X
D
ISDN Hardware Test (#234)
X
ND
Link Quality Test (#233)
X
X
ND
Data Module Internal Loop Around Test (#175)
2
X
ND
Digital Line NPE Crosstalk Test (#9)
X
ND
Port Circuit Information Channel and Control Channel 
Loop Around Test (#13)
X
ND
Data Module Audits Test (#17)
X
X
ND