Lucent Technologies R5SI Manual Do Utilizador

Página de 2643
DEFINITY Enterprise Communications Server Release 5
Maintenance and Test for R5vs/si  
555-230-123  
Issue 1
April 1997
Maintenance Object Repair Procedures 
Page 10-1653
VC-SUMPT 
10
Notes:
a. This port has been busied out with the 
busyout port PCSSpp
 command.
b. The circuit pack has been removed or has been insane for more than 11 
minutes. To clear the error, replace or reinsert the circuit pack.
c. The NPE Crosstalk Test(#1103) failed.
d. The VC Summer Port Local TDM Loopback Test(#1100) failed.
System Technician-Demanded Tests: 
Descriptions and Error Codes
Always investigate tests in the order presented in the table below. By clearing 
error codes associated with the Voice and Control Channel Local Loop Around 
Test, for example, you may also clear errors generated from other tests in the 
testing sequence.
NPE Crosstalk Test (#6)
This test is destructive.
The NPE Crosstalk test verifies that this port’s NPE channel talks on the selected 
time slot and never crosses over to time slots reserved for other connections. If 
the NPE is not working correctly, one-way and noisy connections may be 
observed. This test is part of the port’s long test sequence and takes 
approximately 20 to 30 seconds to complete.
1.
D = Destructive; ND = Nondestructive
Order of Investigation
Short Test 
Sequence
Long Test 
Sequence
D/ND
1
NPE Crosstalk Test (#6) (a)
X
D
TDM Loopback Test (#1100)
X
X
D
Table 10-486.
TEST #6 NPE Crosstalk Test
Error 
Code
Test 
Result
Description/Recommendation
1000
ABORT
System resources required to run this test are not available. The port may 
be busy with a valid call. 
1. Retry the command at 1-minute intervals a maximum of 5 times.
Continued on next page