Packet Bus Fault Isolation and Correction 
Page 9-33
Packet Bus Fault Correction 
9
Part 2:
Processor Port Network:
1. Terminate the Packet Bus so that it extends only from the Active control 
carrier (that is, the carrier that contains the Active SPE) to the carrier that 
contains the Maintenance/Test circuit pack. To allow this procedure to 
isolate the failure to the smallest possible number of carriers, place the 
Maintenance/Test circuit pack into a carrier that contains a processor 
complex, if possible.
2. Determine if the Packet Bus fault is still present. If so, and if there are 
shorts on the Packet Bus, perform Procedure 2 and/or Procedure 3 for 
only the circuit packs in those carriers that are connected to the 
‘‘shortened’’ Packet Bus. (Procedure 2 is performed for port circuit packs, 
and Procedure 3 is performed for processor complex circuit packs.)
3. If the Packet Bus fault is not present, extend the Packet Bus to another 
carrier, and repeat the procedure in the previous step. When a carrier that 
causes the fault to recur is added, and if there are shorts, perform 
Procedure 2 and/or Procedure 3 for only the circuit packs in that carrier.
4. If the Packet Bus fault recurs as the Packet Bus is extended, and if 
Procedures 2 and 3 (if performed) do not resolve the problem, the added 
carrier(s) that caused the problem to recur are defective and must be 
replaced.
Other Port Networks:
1. Terminate the Packet Bus so that it extends only from the carrier that 
contains the Active Expansion Interface to the nearest carrier that contains 
the Maintenance/Test circuit pack. Place the Maintenance/Test circuit 
pack into a carrier that contains an Expansion Interface circuit pack in 
order to allow the procedure to isolate the failure to the smallest possible 
number of carriers.
2. Determine if the Packet Bus fault is still present. If so, and if there are 
shorts on the Packet Bus, perform Procedure 2 and/or Procedure 3 for 
only the circuit packs in those carriers that are connected to the 
‘‘shortened’’ Packet Bus.
3. If the Packet Bus fault is not present, extend the Packet Bus to another 
carrier, and repeat the procedure in the previous step. When a carrier that 
causes the fault to recur is added, and if there are shorts, perform 
Procedure 2 and/or Procedure 3 for only the circuit packs in that carrier.
4. If the packet bus fault recurs as the packet bus is extended, and if 
Procedures 2 and 3 (if performed) do not resolve the problem, the added 
carrier(s) that caused the problem to recur are defective and must be 
replaced.