Cabletron Systems 6C105 Manual Do Utilizador

Página de 38
 
6C105 Overview and Setup Guide
2-1
 
CHAPTER 2
INSTALLATION REQUIREMENTS AND 
SPECIFICATIONS
 
This chapter describes the following:
 
 
Site guidelines that must be met before installing a 6C105 into a rack 
or cabinet
 
 
6C105 configuration guidelines
 
 
Operating specifications for the 6C105 enclosure and power supply 
modules
 
2.1
SITE GUIDELINES
 
The following guidelines must be followed when a site is selected for the 
6C105. If the guidelines are not followed, unsatisfactory network 
performance may result.
 
 
In order to allow proper cooling within the rack, there must be 
3 inches of clearance above the unit and 2 inches of clearance on either 
side of the unit.
 
 
If the 6C105 is to be placed on a shelving unit, the shelf must be able 
to support 75 pounds of static weight.
 
 
If the 6C105 is to be rack mounted, care must be taken to ensure that 
the rack used will support the unit and that the rack remains stable with 
the 6C105 installed.
 
 
The 6C105 ac power supplies require a standard three-pronged power 
receptacle that is located within 6 feet of the site. 
 
 
The temperature of the location must be maintained between 5° and 
40°C (41° to 104°F). Temperature changes of greater than 10°C (18°F) 
per hour must not occur.
 
 
The 6C205-2 DC power supply requires a 10 AWG solid copper 
conducter with #6 ring terminals.
 
Only qualified personnel should install or service this unit.