3-9  Water Reservoir 
The standard water reservoir is rotationally molded polyethylene with a removable lid.  The 
tank is fully insulated to assist maintaining fluid temperature.  All portable chillers shipped 
during the fall, winter, or spring, or those units that are shipped from stock are flushed at the 
factory with a water/ethylene glycol solution to prevent piping components prone to retaining 
water from freezing. During startup and when additional solution is required, refer to the 
ethylene glycol and propylene glycol curves in Figure 11: Ethylene Glycol and Propylene 
Glycol Curves on page 30. Add a pre-mixed solution of industrial quality (not automotive), 
inhibited ethylene glycol or propylene glycol and water to provide freeze protection to a 
temperature 20ºF (11ºC) below the normal chiller operating temperature set point.  
Glycol and/or water, with an inhibitor, should be used to protect the materials (copper, steel, 
stainless steel, and bronze) in the system from corrosion. If you intend to use straight water, 
we strongly advise a minimum leaving water temperature of 45ºF (7ºC) or contact the service 
department. 
Warning!  Operating the chiller setpoint below 45°F (7°C) without the proper 
amount of glycol for freeze protection could result in a damaged 
evaporator.  ACS Group does not warrant the freeze up of the 
evaporator under any circumstances. 
The following glycol products are available: 
Part Number  Description 
A0541358 
Ethylene glycol, 5 gallons (18.9 liters) 
A0539637 
Ethylene glycol, 55 gallons (208.2 liters) 
A0542990 
Propylene glycol, 5 gallons (18.9 liters) 
A0542991 
Propylene glycol, 55 gallons (208.2 liters) 
 
Caution!  Do not connect make-up water directly to the chilled water reservoir unless you 
have an approved automatic water make-up system installed. 
Caution!  Do not pressurize tank. Supply and return connections must be trapped and 
vented to allow vertical risers to drain into tank. Do not overfill system. Allow 
enough free space in tank for vertical piping to drain. 
If your application has chilled water or process piping above the chiller, trap and vent the 
supply and return lines to allow vertical piping to drain into tank.  
Note: 
In applications where the process or process piping is above the reservoir, take 
steps to prevent over pressurization of the reservoir. This condition can occur 
on system shutdown when the water in the system drains into the reservoir. To 
prevent this, a vacuum breaker should be installed at the high point of the “To 
Process” and “From Process” lines.