Cisco Cisco UCS 6120XP 20-Port Fabric Interconnect Manual Técnico
UCS 6140XP−40−port Fabric Interconnect
Replacement or Upgrade for a UCS
6120XP−20−port Fabric Interconnect
Replacement or Upgrade for a UCS
6120XP−20−port Fabric Interconnect
Document ID: 111830
Contents
Introduction
Prerequisites
Requirements
Components Used
Related Products
Conventions
Background Information
Configure
Network Diagram
Verify the connectivity for Ethernet to IOM, L1/L2 ports, Fiber Connection and Operating System of
FI−A
Verify the connectivity for Ethernet to IOM, L1/L2 ports, FC and OS of FI−B
Configure
Configuration with Cisco UCS 6140XP HA connected Fabric Interconnect
Connect to the Cisco UCS 6120XP FI−A and Verify the State of the Cluster HA FI−B
Disconnect the Four 10GbE Cables on FI−B Cisco UCS 6120XP
Place the Four 10GbE Cables onto the Corresponding Ports FI−B Cisco UCS 6140XP
Disconnect the HA L1/L2 Cables on the FI−B Cisco UCS 6120XP
Place the HA L1/L2 Cables Disconnected onto the FI−B Cisco UCS 6140XP
Disconnect the Uplink Ethernet cables FI−B
Place the Uplink Ethernet Cables onto FI−B Cisco UCS 6140XP Corresponding Ports
Prerequisites
Requirements
Components Used
Related Products
Conventions
Background Information
Configure
Network Diagram
Verify the connectivity for Ethernet to IOM, L1/L2 ports, Fiber Connection and Operating System of
FI−A
Verify the connectivity for Ethernet to IOM, L1/L2 ports, FC and OS of FI−B
Configure
Configuration with Cisco UCS 6140XP HA connected Fabric Interconnect
Connect to the Cisco UCS 6120XP FI−A and Verify the State of the Cluster HA FI−B
Disconnect the Four 10GbE Cables on FI−B Cisco UCS 6120XP
Place the Four 10GbE Cables onto the Corresponding Ports FI−B Cisco UCS 6140XP
Disconnect the HA L1/L2 Cables on the FI−B Cisco UCS 6120XP
Place the HA L1/L2 Cables Disconnected onto the FI−B Cisco UCS 6140XP
Disconnect the Uplink Ethernet cables FI−B
Place the Uplink Ethernet Cables onto FI−B Cisco UCS 6140XP Corresponding Ports
Disconnect the Uplink FC Cable(s) FI−B
Place the Uplink FC Cables onto FI−B Cisco UCS 6140XP Corresponding Ports
Optional: Disconnect the Management Console Cisco UCS 6120XP FI−B and Connect onto 6140XP
FI−B Console Port
Remove the GEM (FC Module) from the Cisco UCS 6120XP FI−B
Place the GEM (FC Module) into the Cisco UCS 6140XP FI−B
Return to the FI−B Cisco UCS 6140XP and Start the Configuration Process
Wait until HA is Ready for Cisco UCS 6120XP FI−B with Cisco UCS 6120XP FI−A
Verify
Verification with ICMP Ping
Troubleshoot
Troubleshooting Commands
Related Information
Place the Uplink FC Cables onto FI−B Cisco UCS 6140XP Corresponding Ports
Optional: Disconnect the Management Console Cisco UCS 6120XP FI−B and Connect onto 6140XP
FI−B Console Port
Remove the GEM (FC Module) from the Cisco UCS 6120XP FI−B
Place the GEM (FC Module) into the Cisco UCS 6140XP FI−B
Return to the FI−B Cisco UCS 6140XP and Start the Configuration Process
Wait until HA is Ready for Cisco UCS 6120XP FI−B with Cisco UCS 6120XP FI−A
Verify
Verification with ICMP Ping
Troubleshoot
Troubleshooting Commands
Related Information
Introduction
This document describes the High Availability (HA) process for the installation of a Cisco Unified Computing
System (UCS) 6140XP−40−port Fabric Interconnect Chassis as a replacement or upgrade for a Cisco UCS
6120XP−20−port Fabric Interconnect.
System (UCS) 6140XP−40−port Fabric Interconnect Chassis as a replacement or upgrade for a Cisco UCS
6120XP−20−port Fabric Interconnect.
The UCS 6140XP Fabric Interconnect provides an integrated access layer for the many chassis of server