Samsung AR24KQJSBWKNMG Manual Do Utilizador

Página de 52
51
English
Ins
tallation
Step 4.3  Performing final check and 
trial operation
1  Check the following: 
•  Strength of the installation site 
•  Tightness of pipe connection to detect gas leak 
•  Electric wiring connection 
•  Heat-resistant insulation of the pipe 
•  Drainage 
•  Grounding conductor connection 
•  Correct operation (Take the following steps.) 
2  Press the 
 (Power) button on the remote control to 
check the following: 
•  The indicator on the indoor unit lights up. 
•  The airflow blade opens and the fan gears up for 
operation. 
3  Press the 
 (Mode) button to select Cool or Heat 
mode. Then take the following sub-steps: 
•  In Cool mode, use the Temperature button to set 
the set temperature to 16 °C. 
•  In Heat mode, use the Temperature button to set 
the set temperature to 30 °C. 
•  Check whether, approximately 3 to 5 minutes later, 
the outdoor unit starts, and a cool or warm air 
blows out. 
•  After 12 minutes of stationary condition, check the 
indoor unit air treatment. 
4  Press the 
 (Air swing) button to check whether the 
airflow blades work properly. 
5  Press the 
 (Power) button to stop the trial 
operation. 
Pumping down refrigerant
Pump-down is an operation intended to collect all the 
system refrigerant in the outdoor unit. This operation 
must be carried out before disconnecting the refrigerant 
tubing in order to avoid refrigerant loss to the 
atmosphere. 
1  Shut off the liquid valve with the Allen wrench. 
2  Turn on the air conditioner in cooling with fan 
operating at high velocity. (Compressor will 
immediately start, provided 3 minutes have elapsed 
since the last stop.) 
3  After 2 minutes of operation, shut the suction valve 
with the same wrench. 
4  Turn off the air conditioner and switch mains supply 
off. 
5  Disconnect tubing. After disconnection, protect valves 
and tubing ends from dust. 
  CAUTION
•  Compressor damage may occur if the compressor is 
run at a negative suction pressure.
Pumping down for removing the product
1  Turn on th air conditioner and select Fast Cool mode. 
2  Let the compressor run for more than 5 minutes. 
If the compressor does not operate for more than 
5 minutes due to protection control, wait about 2 
minutes, and then carry out the next procedure. 
3  Release the valve caps on High and Low pressure 
side. 
4  Use L-wrench to close the valve on the high pressure 
side. 
5  After approximately 1 minute, close the valve on the 
low pressure side. 
6  Stop operation of the air conditioner by pressing 
the 
 (Power) button on the indoor unit or remote 
control. 
7  Disconnect the pipes. 
1
2
Gas service port 
<Low pressure>
Liquid service port 
<High pressure> 
1 minute
Off
MG_GOOD_R-410A_A3050_IB&IM_EN_ DB68-06070A-00.indd   51
12-May-16   11:30:06 AM