. BATTERY/CHARGING SYSTEM
16-6
PEOPLE 250
A.C. GENERATOR REMOVAL
A.C. generator removal (!10-3)
A.C. generator installation (!10-6)
REGULATOR/RECTIFIER
INSPECTION
Remove the met-in box. (!2-6)
Remove the regulator/rectifier wire coupler.
Check the continuity between the wire
terminals.
Normal Direction: Continuity
(+) Probe
(-) Probe
I
Yellow
Green
II
Red/White
Yellow
Reverse Direction: No Continuity
(+) Probe
(-) Probe
I
Green
Yellow
II
Yellow
Red/White
VOLTAGE REGULATION TEST
Connect a voltmeter across the battery
terminals.
Start the engine and gradually increase the
engine speed.
The battery terminal voltage should be within
14.0_
15.0V.
A.C.  Generator Stator
Voltage Sensor
Black
Regulator/Rectifier
Bolts
Pulser Coil
Right Crankcase Cover
Green
Red/White
Normal
Direction
Reverse
Direction
Yellow