Run Cable for System 
Run Cables to Base Station Locations 
The Base Station locations should be designated on the building floor 
plans provided to the Polycom field service engineer. Base Stations 
can be mounted easily on raised or acoustical ceiling tiles, or on the 
wall. Avoid locating Base Stations in high or hard-to-reach places, as 
this will hinder maintenance, testing and/or repositioning. 
Wire specifications 
 
The customer’s wire contractor is responsible for adhering to all 
local codes for wiring. 
Polycom recommends UL-listed wire that conforms to the following 
specifications for AWG, distance, and number of power pairs 
required for this installation. 
Power 
Pairs 
Max Cable Feet 
22 AWG 
Max Cable Feet 
24 AWG 
Max Cable Feet
26 AWG 
1 1,100 
750 
470 
2 2,200 
1,500 
940 
3 2,200 
2,200  1,400 
 
 
One additional pair is required for data. 
Attenuation must not exceed 6.8 dB/1,000 feet at 772KHz. 
Wire that is already installed (spare house cable) can be used when it 
is available. House cable will usually run from the MDF in the 
telephone equipment room to intermediate distribution frames (IDFs) 
spread throughout the facility. Install new wire from the closest IDF 
to the Base Station. Be sure no bridge taps, multiples, or “Y” 
connections are created or present. 