Clock Adjustment Problems 
 
No 26MHz clock during Frequency adjustment 
 
Clock adjustment cable not plugged into TIB-OUT 
socket on BTS. 
Unsettled 26MHz during frequency adjustment 
 
Has the BTS been powered up long enough to warm 
up?  Warm up time is normally less than 60 minutes 
but can sometimes take over one hour if the unit has 
been stored in a cold environment before power up. 
 
 
Problems During Beacon Test 
 
No signal seen on other nanoBTS during beacon test 
 
The nanoBTS is not enabled to transmit a beacon 
 
The power level of the beacon BTs is set too low. 
Select a higher power level. 
 
A white list has been applied which does not include 
the beacon channel 
 
If using the external antenna, ensure that the cable 
connections are in place.