In case of emergency, perform these steps IN ORDER: 
 
1.  Press the Red STOP Button. 
2.  Turn the Green Rotary Key Switch to the OFF position and remove the key from 
the transmitter. 
3.  Switch off the main power to the crane. 
4.  Contact your distributor or installer. 
 
 
 
 NOTE:  Read ALL safety information before you install or operate 
this product. 
7.1 Emergency 
Procedures 
If the F22 unit detects an error or system fault, it will issue an emergency STOP command and 
deactivate all systems programmed for a STOP command.  It is therefore important to install the F22 
system correctly so that if it detects a fault, it can perform an emergency stop and the crane will shut 
down safely. 
7.2  General Safety Information 
In an industrial environment, safety must always be a top priority. Persons responsible for 
installation, operation, and maintenance must make certain that both their actions and the equipment 
on which they work are safe. This chapter includes a list of safety rules that must be followed when 
working with TELECRANE products, as well as cranes in general. This list is not intended to be all-
inclusive. General industrial safety rules must always be followed. If there is any doubt about how to 
proceed, always take the safest course of action. 
7.3 Installation 
Safety 
•  Before installing or operating this product, read this manual thoroughly. If you have any 
questions, please contact ITL. 
•  Only qualified personnel who are familiar with the product and who have read these safety 
instructions should install TELECRANE products. 
•  All sources of power to the crane or controlled equipment must be de-energized and applicable 
lockout/tag out procedures executed before installing the unit. 
•  Before installing the receiver, energize it in a controlled environment (for example, an office) 