POWER-UP TESTING AND INITIALIZATION
When shipped from the factory, the T1 ESF CSU ACE is set to factory default conditions.  When power is 
applied, the unit automatically executes self test, followed by an initialization sequence that sets up the 
unit.
Self Test
Upon a power-up or self test, the LCD displays ADTRAN T1 ESF CSU ACE INITIALIZING and the 
LEDs illuminate momentarily. When the self test is completed with no failures detected, the LCD 
momentarily displays ALL TESTS PASSED. If a failure is detected, it is displayed in the LCD window. 
The automatic self test procedure consists of the following steps:
1.
Board level tests - RAM tests; EPROM checksum
2.
Unit level tests - Front panel LED verification