Checkpoint Systems Inc. FISOLRR Manual Do Utilizador
I L S O p e n P l u s E x i t A n t e n n a I n s t a l l a t i o n : D i s a s s e m b l e t h e G a t e s
1-7
Disassemble the Gates
The gates arrive already intact and one must be disassembled when performing an
installation because the gate base is used as the drilling template. Use the slave gate for
this procedure.
installation because the gate base is used as the drilling template. Use the slave gate for
this procedure.
1
Carefully unpack the slave gate from the carton. The side moldings are especially
fragile and can crack when putting significant pressure on them, such as carrying the
entire gate when grabbing the sills.
fragile and can crack when putting significant pressure on them, such as carrying the
entire gate when grabbing the sills.
Figure 1.3
Bottom side screws removal
2
Remove the two screws at the bottom of each side molding.
Figure 1.4
Top screws on side molding removal
3
Remove the two screws from the top of each side molding.
4
Slide each side molding upward 5 cm to 7.6 cm (2” to 3”) towards the top of the gate so
that the hidden fasteners (key hole slots) disengage from the molding strips and are
removed from the upper antenna structure. See
that the hidden fasteners (key hole slots) disengage from the molding strips and are
removed from the upper antenna structure. See
“Sliding the frame side sections down”
on page 1-17
for an illustration.
Note: Do not pry nor bend the moldings outward.
Remove these screws