Use of appropriate safety engineered swivel hoist rings in meter end flanges
Section 2: Mechanical installation
Daniel 3812 Liquid Ultrasonic Flow Meter Installation Manual
May 2015
3-9000-765 Rev H
11.
NEVER apply shock loads to the meter.  Always lift the meter gradually. If shock loading 
ever occurs, the hoist ring must be inspected per manufacturer's recommendations 
prior to be placed in any further service. If a proper inspection cannot be performed, 
discard the hoist ring.
12.
NEVER lift with any device, such as hooks, chains, or cables that could create side pulls 
that could damage the ring of the hoist ring.
13.
NEVER lift more than the ultrasonic meter assembly including electronics and 
transducers with the hoist rings. The only exception is that it is safe to lift the meter 
with one ASME B16.5 or ASME B16.47 blind flange bolted to each end flange of the 
meter. NEVER use the hoist rings on the meter to lift other components such as meter 
tubes, piping or fittings attached to the meter. Doing so will exceed the load rating of 
the hoist rings.
14.
Remove the hoist rings from the meter after lifting is completed and store them in an 
appropriate case or container per their manufacturer's recommendation.
15.
Apply heavy lubricant or anti-seize to the threads of the plug bolts and reinstall the plug 