MELSEC-Q
8   TROUBLESHOOTING 
 
8 TROUBLESHOOTING 
In order to ensure high system reliability, it is important to take precautions before the 
system is operated and to quickly and effectively correct problems if they do occur.   
This is why it is important to perform off-line testing of the network and checking of the 
cables when first starting the system. 
Make sure to perform the following checks, which are explained in Chapter 4, "Setup 
and Procedures Before Starting the Operation." 
1)  Standalone operation check and operational setting of the network module 
2) Offline 
tests: 
 
Hardware test, Internal self-loopback test, self-loopback test and forward 
loop/reverse loop test. 
3)  Check the connection of the data link cable. 
Network diagnostic loop test (requires optical system) 
 
Even with this, if an error does occur, it is important to quickly and accurately 
understand the nature of the problem. The following are three methods for confirming 
the contents of an error. 
 
(1)  Network diagnostics to remote master station with GX Developer 
(a)  Network monitor (refer to Section 8.1) 
The status of the following four types of networks can be checked by 
monitoring the line: 
1)  Status of the entire network: Host information 
2)  Data link status and parameter status, etc. of each station:   
Other station information 
3)  Control station information, detailed data link information, etc.:   
Network monitor details 
4)  Loop switch count, line error, communication error, etc.:   
Error history monitor 
(b)  Diagnostic tests (refer to Sections 4.10) 
The following four items can be checked or executed through the diagnostic 
tests: 
1)  Wiring status (IN/OUT, etc.) of the data link cable:   
Loop test (required for optical loop system) 
2)  Setting status of numbers: whether the same station number has been set 
for two or more stations, whether two or more control stations/remote 
master stations exist, network numbers, and group numbers: Setup 
confirmation test 
3)  The order of stations connected in the direction of the forward loop and 
the reverse loop: Station order check test 
4)  Setting status of the routing parameters: Communication test 
 
(2)  Confirmation by error code: Refer to Section 8.3 
When either cyclic transmission or transient transmission using link dedicated 
instructions or GX Developer (communication with other stations) was not 
normally performed, an error code is stored in the link special register and the 
system monitor. 
The contents of the error can be checked using this error code. 
 
(3)  Confirmation by the LEDs on the front of the network module 
(Refer to Section 4.2) 
With the LED displays, the following errors can be checked: whether the host is 
operating or stopped, whether the station acts as a control station or a normal 
station, whether the baton pass is being executed, whether data linking is being 
executed, whether data are being transmitted/received, and whether any error 
has occurred. 
(4)  Confirmation of the error history of the entire system (Refer to 
Section 8.3) 
By using GX Works2, the error history of the entire system can be checked even 
after errors were cleared by turning on and off the programmable controller or by 
resetting the programmable controller CPU. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 