24 Vdc SDC Burner Manual
Section: Drive Component Maintenance
Drive Component 
Maintenance
A. Motor, Blower Wheel, & Coupling 
Replacement
The motor will require replacement if the proper voltage is 
measured at the motor input, and the motor will either not 
run, or the current draw with a free running pump exceeds 
10% of the rated current.
To replace the burner motor, coupling and/or blower wheel 
perform the following steps.
Before servicing, turn off and/or disconnect all power 
to the burner.
Disconnect the burner motor wires.
Remove the bolts securing the motor to the burner 
housing.
Remove the motor, coupling, and blower wheel.
Loosen the set screw on the blower wheel to slide 
the existing wheel off the shaft.
Slide the new blower wheel onto the old shaft (after 
thoroughly cleaning housing) and/or slide the old 
blower wheel onto the new motor shaft.
When replacing the blower wheel, verify the wheel 
is centered between the two sides of the burner 
housing as shown.
Rotate the blower wheel until the set screw is 
centered on the fl at of the motor shaft.  Tighten the 
set screw to secure the wheel.
Slide the motor coupling on the motor shaft then 
install the motor on the burner housing. Insure that 
the motor coupling fi ts between the motor shaft and 
the pump shaft inside the housing. Tighten the motor 
retaining screws. Reconnect the wires.
Restore power, start the burner and perform the 
combustion test described previously in this manual.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Figure 7. – Blower Wheel
CENTER WHEEL FOR EQUAL 
DISTANCE FROM HOUSING SIDES
B. Pump Maintenance
General Pump Information
Important information - Long or oversized inlet lines may 
require the pump to operate dry during initial bleeding period. 
In such cases, the priming may be assisted by injecting fuel 
oil in the pump gear set. Under lift conditions, lines and fi ttings 
must be air tight. To assure this, “Pipe Dope” may be applied 
to both the used and unused inlet and return fi ttings. Do NOT 
use Tefl on tape or compression fi ttings.
 
Mounting Position
Beckett CleanCut pump may be mounted in any position 
(except upside-down in a  single pipe installation).
Vacuum Check
A Vacuum Gauge may be installed in either of the 1/4” 
NPT inlet ports.
Pressure Check
Use the nozzle port when performing a pressure check. 
If the bleed port is used, the reading on the gauge should 
be approximately 5 psig higher than the pressure reading 
on the nozzle port. See Figure 8.
Cutoff Check
To check cutoff pressure dead head a pressure gauge in the 
nozzle port. Run the burner for a short period of time. Shut the 
burner off. The pressure will drop and hold above zero.
Pressurized or gravity feed installations
These installations must not exceed 3 psig on inlet line or 
return line at the pump per NFPA 31. A pressure greater 
than 10 psig may cause damage to the shaft seal.
Figure 8. – Oil Supply Components
Bleed Port