Installing Support Brackets (Figure 58)
A horizontal pipe support MUST BE used for each 3 feet of horizontal 
run. The pipe supports should be placed around the  pipe and nailed 
in place to framing members. There MUST BE a 3 inch clearance 
to  combustibles  above  8  inch  diameter  pipe  and  elbows  and  1 
inch clearance on both sides and bottom of the 8 inch dia. pipe to 
combustibles on all horizontal pipe sections and elbows. 
Vertical runs of this vent systems must be supported every 4 feet 
above the appliance flue outlet by wall brackets attached to the 
8 inch vent pipe and secured with nails or screws to structural 
framing members.
 
Figure 58
Installing Firestops (Figures 59, 60, 61, and 62)
Firestops are required for safety whenever the vent system passes 
through an interior wall, an exterior wall, or a ceiling. These firestops 
act as a firebreak heat shield and as a means to insure that minimum 
clearances are maintained to the vent system.
Horizontal runs in the vent system which pass through either interior 
or exterior walls, require the use of wall firestops on both sides of 
the wall through which the vent passes.
Cut  a  10-3/8  inch  x  12-3/8  inch  hole  in  wall.  Position  firestop 
(SD1249) on interior side of wall for 10-3/8 inch x 12-3/8 inch 
hole.
Attention: Wall firestop hole is off-set towards bottom of wall 
opening. Secure with nails or screws. Continue the vent run through 
the firestop. See Figure 59.
10 3/8
12 3/8
WALL FIRESTOP
HOLE IS OFF-SET
TOWARDS BOTTOM
OF WALL OPENING.
Figure 59
Vertical runs of this system which pass through ceilings require the 
use of ONE (1) ceiling firestop at the hole in each ceiling through 
which the vent passes.
Position a plumb bob directly over the center of the vertical vent 
component and mark the ceiling to establish the center point of the 
vent. Drill a hole or drive a nail through this center point and check 
the floor above for any obstructions such as wiring or plumbing 
runs. Reposition the appliance and vent system, if necessary, to 
accommodate ceiling joists and/or obstructions.
Cut a 10 1/2 inch x 10 1/2 inch hole through the ceiling, using the 
center point previously marked. Frame the hole with framing lumber 
the same size as the ceiling joists. See Figure 60. If the area above 
the ceiling is NOT an attic, position and secure the ceiling firestop 
on the ceiling side of the previously cut and framed hole. See Figure 
61. If the area above the ceiling is an attic, position and secure the 
firestop on top of the previously framed hole. See Figure 62.
NOTE: 
Remove insulation from the framed area in the attic before 
installing the firestop and/or vent pipes.
8" VENTING FRAMING AND FINISHING