NetworkAIR FM DX 60 Hz Operation, Maintenance, and Troubleshooting
9
Commissioning
After installation, verify that all components are working properly and that the Module is ready to 
begin operation. Before you commission the Module, make sure that the following inspections are 
completed:
•  Initial 
•  Electrical 
•  Mechanical 
•  User interface 
After these inspections are complete, the Module is ready for the functional test and charging. 
Complete the following procedures to begin operation of the Module:
•  Functional test
•  Module charging
After you complete the following two checklists, the Module is ready to begin normal operation:
•   Start-up
•   Final
Electrical Hazard: Perform Lockout/Tagout procedures on the equipment being 
serviced. Failure to remove power before servicing this equipment could result in 
serious injury or death.
The initial inspection ensures that the Module has been securely mounted to the floor stand or 
sub-base and that the air distribution system is properly installed. The room must be sealed with a 
vapor barrier and the Module must be free of damage.
Caution: Do not run service utilities in front of the blower outlets.
Caution: The vapor barrier minimizes moisture infiltration. Without a vapor barrier, your 
equipment will have difficulty maintaining the humidity in the room. 
Do not introduce unconditioned outside air into the space.
Note: 914 mm (36 in ) of clear floor space in front of the equipment is required for 
service access.
Electrical inspection. 
The electrical inspection verifies that all electrical connections are secure 
and correct and that the Module is properly grounded.