Справочник Пользователя для Emerson 308014EN

Скачать
Страница из 166
10-43
Rosemount Tank Radar REX
Chapter 10 Mechanical Installation
Installation Manual
308014EN, Edition 4
May 2013
10.4.5 Installation on the tank.
Follow this step by step instruction when installing the LPG/LNG Gauge. 
Note!
There must be a clear mark on the pipe flange to show the direction of 
the reference pins in the still pipe. Carefully check that the Closing is 
mounted in the appropriate angle relative to that mark. 
The Lower Flange, the ball valve and the Closing are preassembled and 
delivered as one unit. 
1
Check that all parts and tools 
are available before carrying 
them to the tank top.
2
Install the still pipe according to 
mechanical installation drawing 
9150072-924.
3
Enter the Cone into the still 
pipe to make sure it fits. Maxi-
mum gap between the Cone 
and the pipe is 2 mm.
4
Mount the Pipe Cone onto the 
Closing using four M6 Allen 
head screws. Be careful when 
handling the Closing with the 
Pipe Cone mounted onto it as it 
is very important that the Pipe 
Cone is not deformed. 
Do not remove the yellow pro-
tective cap.
3960_Install.eps
Pressure 
transducer
Do not remove this 
protection cap
Lower 
flange
Closing
Four M6 screws
Pipe cone
Ball valve