Chapter 2  Installation      15 
ACTURA Flex 48330
 
Power System  User Manual 
2.2  Installation Procedures 
2.2.1  Cabinet Installation 
Installation on the floor 
Step 1: mark the position where the power system is to be installed. 
Determine the installation position of the power supply cabinet in the power room 
according to the installation chart. Based on the mechanical specifications (see Fig. 
2-1) of the installation holes of the power supply cabinet, determine the accurate 
position of the center points of the installation holes on the floor, and mark them 
with a pencil or oil pen. 
 
(Applicable to the cabinet with 600mm depth) 
 
(Applicable to the cabinet with 600mm depth) 
Figure 2-1  Installation dimensions of the cabinet base 
Step 2: drill reserve holes. 
The expansive pipes delivered with the power system are M10
%55mm, therefore, 
use electric drill with drill bit 
Φ12 and depth 70mm to drill holes at the center points 
of the installation holes marked on the ground. To avoid being off-center, be careful