The active redundant parallel operation will switch 
automatically to the increase power mode if more power is 
required at the output of the UPS. This implements that the 
redundancy level decreases or will diminish completely. On the 
other hand the level of redundancy of the UPS will increase if 
the power consumption on the output decreases.  
The distribution generally is realised in the low voltage main 
distribution (LVMD) where the external and the following sub 
distribution for connected load circuits takes place. Such 
parallel control panels in wall cabinets including an external HU 
as well as input and output control panel can also be ordered 
via AEG Power Supply System and their partners. 
9.2 
Setup / connection of the parallel operation field 
The mains connection of each UPS is realised analogue to 
the description in chapter 5. 
 
For the single phase mains connection for each 
UPS the same phase has to be used, i.e. all 
UPS have to use either L1 or L2 or L3 (no mix!). 
The supply of the multi pole central external 
manual bypass has to be realised with this 
phase.  
The UPS outlets are connected via separator with the parallel 
operation bus-bar. At this point the instructions of chapter 5 
are to follow.  
The following applies for output and input lines of the UPS: 
The difference in length of the lines with a line length of up to 
20 m may not vary more the 20% and with more than 20 m 
not more than 10%.  
The default bridge between “JP1” and “JP2” in the control 
panel of every UPS has to be removed. The distribution of the 
output has to be executed according the instructions of 
chapter 5. Please take care of the exact labelling of the 
elements to prevent any operation error. The communication 
between the parallel connected units is realised with the 25 
pole parallel operation line that comes with the UPS.