B. Sequence of Operation
This icemaker utilizes a thermostatic bin control to switch the gear motor, fan motor, and 
compressor on and off as needed. This icemaker utilizes a float-operated water valve in 
the water reservoir to allow water into the icemaker as needed. After the power switch is 
placed in the "ON" position, the sequence is as follows: 
1. Freeze Cycle
GM, FM, CR, and Comp energize. As the water in the evaporator cools, ice starts 
forming within 4 to 6 minutes. This time frame depends on the inlet water and ambient 
temperature conditions. 
The float-operated water valve allows water into the reservoir as needed to continue the 
ice making process. This continues until BC shuts down the icemaker or power is turned 
off to the icemaker. 
2. Bin Control Thermostat Shutdown
Ice fills storage bin to level of BC. When BC opens, GM, FM, CR, and Comp de-energize. 
When ice level lowers and BC closes, the icemaker starts operating again.
C-100BAF Series Sequence Flow Chart and Component Operation
2. Shutdown
1. Freeze Cycle
The float-operated water valve allows 
water into the reservoir as needed to 
continue the ice making process.
When BC opens, the icemaker shuts 
down. When BC closes, the icemaker 
starts operating again.
Full Bin
BC closed
GM energized
FM energized
CR energized
Comp energized
Power Switch  
"ON"
BC closed
GM continues
FM continues
CR continues
Comp continues
BC open
GM de-energized
FM de-energized
CR de-energized
Comp de-energized
BC open
BC closed
Legend: 
BC–bin control thermostat; Comp–compressor; CR–compressor relay; 
FM–fan motor; GM–gear motor