10   HIGH-LEVEL POSITIONING CONTROL 
 
10.6 Start program for high-level positioning control 
10.6.1 Starting high-level positioning control 
To execute high-level positioning control, a sequence program must be created to start 
the control in the same method as for major positioning control.   
 
The following shows the procedure for starting the "1st point block start data" 
(regarded as block No. 7000) set in axis 1. 
 
1500
Y10
1501
CPU module
7000
1
ON
QD75
Input/output signal 
 
Drive unit 
Buffer memory  
Control by designated
positioning data
1)
3)
2)
4)
    (This establishes that the control as "high-level positioning control" using block start data.)
2) Set the point No. of the "block start data" to be started. (In this case "1".)
3) Turn ON the start signal.
When carrying out a positioning start with the 
next scan after a positioning operation is 
completed, input signal X10 as an interlock so 
that the start is carried out once the X10 signal 
turns OFF after the Y10 signal turns OFF.  
1) Set "7000" in " Cd. 3 Positioning start No.".
4) The positioning data set in the "1st point block start data" is started. 
 
Fig. 10.2 High-level positioning control start procedure