1   PRODUCT OUTLINE 
 
1.2.2 Outline of starting 
The outline for starting each control is shown with the following flowchart. 
It is assumed that each module is installed, and the required system configuration, 
etc., has been prepared. 
 
 
Flow of starting
Preparation
Installation and connection of module
Setting of hardware
Control 
functions
Major position-
ing control
•Block start (Normal start)
•Condition start
•Wait start
•Simultaneous start
•Repeated start
•Machine OPR control
•Fast OPR control
•JOG operation
•Manual pulse generator operation
Positioning 
parameters
Set the OPR parameters. 
Positioning
data
Set the positioning data. 
Set the block start
data. 
Control data
Set the positioning 
starting point No.
Set the manual pulse 
generator enable flag to "1".
Set the manual pulse generator
1 pulse input magnification.
Input the start signal.
Method (2) Issue the Z.PSTRT instruction from the CPU module
Method (3) Turn the QD75 external start signal ON
Operate the 
manual pulse 
generator
Control start
Control end
Operation
Stop
Set the positioning parameters.
to            ,
)
Pr.1
Pr.42
 )
Pr.150
to
)
Da.1
)
Da.10
to
)
Pr.43
)
Pr.57
to
)
Da.11
)
Da.19
)
)
Cd.3
)
)
Cd.4
)
)
Cd.17
)
)
Cd.21
)
)
Cd.20
•Inching operation
)
)
Cd.16
Set the inching 
movement amount 
to other than 0.
)
)
Cd.16
Set the inching 
movement 
amount to 0.
OPR parameters
Block start data
Set the positioning start No.
Start signal
Method (1) Turn ON the QD75 start signal from the 
                   CPU module
Turn the QD75 JOG start signal 
ON from the CPU module
•Position control
•Speed control
•Speed-position 
 switching control
•Position-speed 
 switching control
•Other control
High-level positioning 
control
OPR control
•Machine OPR control
 
Manual control
 
•Manual pulse generator operation