Installation
40
F232062
Mechanical Installation
 (Continued)
Figure 34
4. Use rebar or other appropriate material to 
ensure that the concrete foundation pad 
will be sufficiently connected to the 
existing floor.
5. Prepare a form for the above-ground 
portion of the pad and fill form and 
excavation with concrete to join the 
foundation. Verify that top of pad is level. 
The height of the pad must not exceed 
8 inches (203 mm).
6. Use the mounting bolt layout in Figures 
27 and 28 to properly position the 
mounting bolts in the wet concrete. 
When using J-bolts, allow 1-1/2 inches 
(38 mm) to extend above the surface of 
the concrete.
7. Allow concrete to dry.
8. Place the machine carefully over the 
mounting bolts. Never attempt to lift the 
machine by the door handle or by pushing 
on the cover panels.
9. If the machine is a 2-speed model, 
grouting is optional.
If grouting is not desired, position washers 
and locknuts on J-bolts and tighten the 
locknuts by even increments—one after 
the other—until all are tightened evenly 
and the machine is fastened securely to the 
floor. See Figure 35.
If grouting is desired, proceed to step 10.
If the machine is a 3-speed or variable-
speed
 machine installed on a concrete 
foundation pad, the machine must be 
grouted. Proceed to step 10.
H036IE3A
Pad height
must not exceed
8 in. (203 mm).
1 in. (25 mm) minimum
4 in. (102 mm)
minimum