SECTION 4 TYPICAL INSTALLATION
WARNING: All life safety and electrical codes must be strictly followed.
Installation Overview
As with any Monitoring System, each application can be different. Use the guidelines below as a basic
understanding of what a standard application would be like.
1. Seek prior approval from local life safety officials prior to installing any locking system.
2. Identify all equipment to be installed and inspect for any damage that may have resulted during shipment. If
understanding of what a standard application would be like.
1. Seek prior approval from local life safety officials prior to installing any locking system.
2. Identify all equipment to be installed and inspect for any damage that may have resulted during shipment. If
damage is found notify the carrier immediately and arrange for inspection. Be sure to retain all shipping and
packaging materials.
packaging materials.
3. Install any communication and/or power wires, if necessary from the Node to the appropriate power/data
location. Leave sufficient extra length to allow for node placement adjustments.
4. The location of the Nodes is provided by the system configuration documentation. Mount as required. Standard
application would place this equipment on the wall 5’ to 10’ off the floor.
5. Make all necessary wiring connections as shown in Section 9 of this manual.
6. Plug in all power supplies to un-switched, backed up power sources. Do not connect to a switched receptacle
7. The system is now ready for tuning, programming, and testing
6. Plug in all power supplies to un-switched, backed up power sources. Do not connect to a switched receptacle
7. The system is now ready for tuning, programming, and testing
Determine if the system is Wired or Wireless
The method that the nodes will be communicating and how they are to be powered is provided with the system
configuration documentation.
configuration documentation.
Wired connection
Connect the node to the network port with Cat 5A Ethernet cable for the ENVisionIT network.
If using Power over Ethernet (POE), the switch must meet IEEE Class 4 POE+
If using a central power supply the power cables will need to be run.
If using Power over Ethernet (POE), the switch must meet IEEE Class 4 POE+
If using a central power supply the power cables will need to be run.
Network Structure
The ENvisionIT RTLS network is intended to be an isolated network. Connections to existing infrastructure
networks should be only be done after careful planning.
networks should be only be done after careful planning.
Wireless connection
The ENVisionIT node can connect wirelessly via 802.11 a/b/g to the Secure Care ENVisionIT network. Once
connected, the node will attempt to automatically join and build the RTLS network. The nodes will communicate
between themselves via UWB and WiFi.
connected, the node will attempt to automatically join and build the RTLS network. The nodes will communicate
between themselves via UWB and WiFi.
Mounting the Nodes
The nodes can be mounted in several ways.
Flush Wall Mounted
Suspended ceiling mount.
There are mounting holes in the base that allow for wall mounting or there is an option of using ceiling clips to
mount the node to the grid of a dropped ceiling.