Справочник Пользователя для Binsfeld Engineering Inc TX10K-LP
- 16 -
Multiple TX10K Transmitters
When working with multiple TX10K Transmitters in close proximity,
the Infrared Receivers may be intentionally covered with an
opaque object in order to eliminate an inadvertent configuration
change to an adjacent TX10K. Also, removing power
(disconnecting the battery) or putting the TX10K in standby mode
will prevent the RM10K from changing the configuration of a
transmitter.
When working with multiple TX10K Transmitters in close proximity,
the Infrared Receivers may be intentionally covered with an
opaque object in order to eliminate an inadvertent configuration
change to an adjacent TX10K. Also, removing power
(disconnecting the battery) or putting the TX10K in standby mode
will prevent the RM10K from changing the configuration of a
transmitter.
Product Safety
The user assumes all risk and liability for the installation and
operation of this equipment. Each application presents its own
hazards. Typically, certain system components are strapped to a
rotating shaft. If sufficient care is not taken to properly secure
these components or accessories connected to them, they can be
flung from the shaft, causing damage to the components or to
property or persons in the vicinity. Use more than enough tape:
10 or more wraps is not too much.
operation of this equipment. Each application presents its own
hazards. Typically, certain system components are strapped to a
rotating shaft. If sufficient care is not taken to properly secure
these components or accessories connected to them, they can be
flung from the shaft, causing damage to the components or to
property or persons in the vicinity. Use more than enough tape:
10 or more wraps is not too much.
Installation Procedure
The TorqueTrak 10K System is designed for ease of use. The
procedure for a typical setup on a shaft for obtaining torque
measurements is detailed in the Field Testing section below.
It is recommended that the user bench test the instrument to
become familiar with the various operational features prior to
conducting tests in the field. The BS900 Bridge Simulator and 9V
Battery Connector have been provided for this purpose. See the
Bench Testing section for details.
procedure for a typical setup on a shaft for obtaining torque
measurements is detailed in the Field Testing section below.
It is recommended that the user bench test the instrument to
become familiar with the various operational features prior to
conducting tests in the field. The BS900 Bridge Simulator and 9V
Battery Connector have been provided for this purpose. See the
Bench Testing section for details.