Справочник Пользователя для Appareo Systems LLC 1535103

Скачать
Страница из 9
 
Installation Manual 
Rev: 1.2 
Last Revised: 3/22/16 
 
 
Document Number: 600840-000038 
Page 6 of 9 
 
 
3.2.  INSTALLATION INSTRUCTIONS OVERVIEW 
System installation is accomplished in the following steps: 
1)  Installation of Gateway into the tractor cab headliner 
a.  Torque the antenna terminations to Gateway RF SMA connectors with a torque 
spec of 7-10 in-lbs +/- 0.5 in-lbs. Mount the 
Gateway enclosure to the cab with ¼” 
or 6-mm fasteners and a torque of 30 in-lbs. 
2)  Installation of Antennas 
a.  Find a location on the equipment such that the following distances are the 
minimum spacing between system components. 
Table 1 System Component Minimum Spacing 
 
Operator  
Gateway 
Antenna Hub 1  
(Recommended minimum 
spacing between antenna 
hubs is 7.5 cm) 
40 cm (USA) 
60 cm (Canada) 
20 cm 
Antenna Hub 2 
40 cm (USA) 
60 cm (Canada) 
20 cm 
Gateway 
20 cm 
N/A 
 
b.  Ensure the antennas have a ground place of 300 x 300 mm around them. 
c.  Torque the antenna mounting nut (M14x1) to 30 +/- 0.5 in-lbs. 
  
 
 
3.3.  PARTS LIST FOR INSTALLATION 
The following parts are required for the installation of Gateway. 
Table 2 Parts List for Installation 
Parts List for Installation
 
Item 
Nomenclature 
Part Number 
QTY 
Gateway 
153510-000003 
Antenna Hub 1 
NA 
Antenna Hub 2 
NA