QC Guide of Active Hub  
 
 
Jul. 13 
Part Profile 
 
 
Front View 
 
 
 
Rare View 
Plan of QC Activity 
Ensuring timely completion of Product by the CM (Contract Manufacturer): 
To ensure that QC activity is performed on the defined and agreed dates with the CM in accordance with the PO dates. It is 
important that the CM also executes the project plan on timely manner; and completes all tasks on agreed dates. So the first 
stage is to ensure that CM follows the defined milestones for the timely completion of the product which are; 
Milestone# 1 (1~3 days after P.O) 
Items  
Confirmation Day from CM 
for ordering the parts 
Active hub PCB  3
rd
 Day after P.O 
Connector 
3
rd
 Day after P.O 
MW Adapter 
3
rd
 Day after P.O 
Power Cord 
3
rd
 Day after P.O 
Metal casing 
3
rd
 Day after P.O 
Packaging 
3
rd
 Day after P.O 
 
Position of “Display” and 
“TSU” is opposite now 
Position of “Enable” and 
“Disable” is opposite now