FRAMING AND FINISHING
Installing Support Brackets (Figure 38)
A horizontal pipe support MUST BE used for each 3 feet of horizontal 
run. The pipe supports should be placed around the  pipe and nailed 
in place to framing members. There MUST BE a 3 inch clearance 
to combustibles above 6 5/8 inch diameter pipe and elbows and 
1 inch clearance on both sides and bottom of 6 5/8 inch pipe to 
combustibles on all horizontal pipe sections and elbows. 
Vertical runs of this vent systems must be supported every 4 feet 
above the appliance flue outlet by wall brackets attached to the 6 
5/8 inch vent pipe and secured with nails or screws to structural 
framing members.
 
Figure 38
Installing Firestops
Firestops are required for safety whenever the vent system passes 
through an interior wall, an exterior wall, or a ceiling. These firestops 
act as a firebreak heat shield and as a means to insure that minimum 
clearances are maintained to the vent system.
Horizontal Firestops (Figure 39)
Horizontal runs in the vent system which pass through either interior 
or exterior walls, require the use of wall firestops on both sides of 
the wall through which the vent passes.
Position the firestops on both sides of the framed hole, previously 
cut. Refer to Figure 24 on page 20 for sizing information. Secure 
firestop  with  nails  or  screws.  The  heat  shields  of  the  firestops 
MUST BE placed towards the top of the hole. Continue the vent 
run through the firestops. 
Figure 39
WALL FIRESTOP