Справочник Пользователя для Mitsubishi Electronics ETH-1000

Скачать
Страница из 36
 
 
2-1 
Chapter 2 
System Overview 
A  Verification  System  is  used  as  a  test  bed  for  verifying  the  steps  documented  in  this  Quick  Start  guide.  The 
Verification System is shown in Figure 2 below with the IP address assignments of all the devices.  
 
Netgear Switch
Monitoring Laptop 2
192.168.1.5
ControlLogix
192.168.1.30
ICC
192.168.1.102
iQ (Built-in Ethernet Port)
192.168.1.40
iQ E71 Ethernet Module
192.168.1.45
iQ System
 
Figure 2 Architecture of an Example Verification System 
The  Verification  System  consists  of  one  monitoring  PC  (e.g.  Monitoring  Laptop  1),  a  ControlLogix  system,  an 
ICC ETH-1000 module, and one Mitsubishi Q13UDEH PLC system. 
The  following  list  contains  high-level  steps  to  establish  proper  EtherNet/IP  communication  of  this  Verification 
System. Each of these steps will be further detailed in subsequent chapters 
1.  Connect the programming/monitoring PC, Rockwell PLC, ICC ETH-1000, and Mitsubishi PLC system to 
the Ethernet network 
a.  Configure all devices to have proper IP addresses and subnet masks as shown above. 
b.  Ensure that RSLogix5000, ICC Gateway Configuration Utility, and Mitsubishi GX Works2 or GX 
Developer software packages are installed on the programming PC. 
2.  Create a project using the RSLogix5000 software to interface with the Mitsubishi PLC. 
a.  Add the ICC ETH-1000 as a Generic Ethernet Module in the RSLogix5000 project. 
3.  Configure ICC ETH-1000 
a.  Configure EtherNet/IP Parameters 
b.  Map the ControlLogix Tags for the ETH-1000 to the internal ETH-1000 database locations 
c.  Map ICC ETH-1000 internal database locations to proper controller register and/or bit locations 
for the PLC. 
4.  Configure iQ system 
a.  Configure the Built-in Ethernet port on the iQ CPU 
b.  Configure the Ethernet port on an external Q71E71 module if necessary