Power up procedure  71 
This process helps to ensure personnel safety during the electrical start up of the HP POD 20c. 
  
 
WARNING:
  To avoid risk of personal injury or loss of life, do not open an energized POD 
electrical cabinet without an energized work permit and appropriate PPE. 
  
 
Cold weather power up checklist 
Site electrical 
Open (verify open) all site POD feeder supply breakers. 
Site mechanical 
Verify that the POD supply and return isolation valves are closed. 
POD mechanical 
Open (verify open) POD chilled water return butterfly isolation valve. 
POD electrical 
 
Hot aisle—Verify that all IT power drop box breakers on the power tap boxes are open. 
 
Cold aisle: 
a. 
Close all breakers and fuses within the control cabinet. 
b. 
Close and latch the ECS cabinet. 
c. 
Position the EPO system (on page 
) to Armed (White) or Bypass (Green). 
d. 
Verify that all EPO activation buttons are in the reset position (not depressed). 
e. 
Position the 24V DC power switch to On. 
 
Main power feed cabinet: 
a. 
Close main power feed breakers A and B. 
b. 
Verify power surge fuses are installed. 
 
House power and critical IT power cabinets: 
a. 
Close all fuses in the house power and critical IT power cabinets. 
b. 
Close all non-spare breakers in the house power and critical IT power cabinets. 
c. 
Close and lock both house power and transformer cabinet doors. 
 
Standard power up procedure 
Perform the following procedures in the exact order in which they are listed. 
 
Site electrical 
Close all POD site power feeder breakers and monitor for any effects that are not standard. 
 
ECS and EPO 
Verify the following using the ECS touchscreen and EPO indicators: 
 
The ECS panel is operational and displays the user interface. 
 
POD lighting is operational.