SAFETY - 17
INTERLOCK 
 
Electron Gun 
The Gun cable is now interlocked with a momentary switch.     
If the cover at the top of the electron gun is removed to 
disconnect gun cable, the High Voltage applied to the electron 
gun is shut off.    This switch can be overridden for service.   
However, if the cable is replaced the service override is removed. 
Ion Pump 
The ion pump cover at the back of the electron optical column 
has a safety interlock switch.    If the cover is removed, the High 
Voltage supplied to the ion pumps is shut off and lamps in the 
RESET switches for ion pumps located on the evacuation control 
panel will go off.    For service the switches can be overridden, 
but as soon as the ion pump cover is put again, the service 
override is removed. 
Other High Voltages 
High voltage power supply for photo multipliers and electrodes 
are placed inside of a box located at the behind of the specimen 
chamber. The cover of the box has a safety interlock switch. If 
the cover is removed, the High Voltage supplied to the photo 
multipliers and electrodes is shut off. For service the switches 
can be overridden, but as soon as the cover is put again, the 
interlock is functional.   
Baking power supply        Baking heater power supply connectors are placed at the right 
side of the ion pumps cover. To connect heater connectors, the 
box cover of the connector must be removed. The box cover of 
the connector has a safety interlock switch. The baking power is 
shut off when the cover is removed. After connecting connectors, 
put the cover again. The baking power then becomes applicable.   
Unit power supply           Four side covers of the Main unit have safety interlock switches 
one for each. If one of the side covers is removed, AC power 
supply for the Main unit (for evacuation system, ion pump power 
supply and stage controller) will be shut off. The switches can be 
overridden for service.    However, if the covers are put again, the 
service override is removed.     
The interlock location is shown in fig S-6 
Protection for Earthquakes  It is recommended that the protection for movement of Main unit 
and Display unit during earthquakes is to be provided by user as 
shown in figures S-7 and S-8. 
Gravity location of units            The gravity location of Main and Display unit are shown in fig S-
9 through S-11.   
Water-leakage detection          It is recommended that the water–leakage detector is to be 
provided by user. Figure S-12 shows an example of the water–