XI Start-up and Checkout
Use the following procedure for initial start-up of the boiler:
1)  If not already done, fl ush the system to remove sediment, fl ux, and traces of boiler additives. This should be  
 
done with the boiler isolated from the system.
2)   Fill the boiler and hydronic system with water meeting the following requirements below (also see the note on the next 
page):
 
 pH between 6.5 and 8.5
 
 Total Solids less than 2500 PPM
 
 Hardness less than 120 PPM (7 Grains/Gallon)
 
 Pressurize the system to at least 12 psi at the boiler
3)  Check all new piping for leaks and purge piping sections that are fi lled with air. See the National Fuel Gas Code for 
additional information on testing and purging gas lines. 
4)  Vent system must be complete and free of obstructions before attempting to fi re boiler. Make sure that the silicone cure 
time called for in the vent assembly instructions has passed before fi ring boiler.
5)  Inspect all line voltage wiring for loose or uninsulated connections.
6)   Remove the dust cap from the condensate trap (Fig 7.21).  Add water to the trap until water runs out the condensate 
drain.  Reinstall the dust cap.
NOTE
SAFE LIGHTING AND OTHER PERFORMANCE CRITERIA WERE MET WITH THE GAS 
TRAIN ASSEMBLY PROVIDED ON THE BOILER WHEN THE BOILER UNDERWENT 
THE TEST SPECIFIED IN Z21.13.
WARNING
 NEVER ATTEMPT TO FILL A HOT EMPTY BOILER
WARNING
•   NEVER USE A FLAME TO CHECK FOR GAS LEAKS.
•   MAKE SURE THAT THE AREA AROUND THE BOILER IS CLEAR AND FREE FROM  
    COMBUSTIBLE MATERIALS, GASOLINE AND OTHER FLAMMABLE VAPORS AND  
    LIQUIDS