2-9
Model NGA2000 HFID 
2-6 INSTALLATION 
CONSIDERATIONS 
CHECKLIST 
Verify the following: 
•  The Analyzer’s location should be: 
Clean 
A well ventilated area 
weatherproofed 
Non-hazardous 
Vibration-free 
Have stable ambient temperature 
•  The gas cylinders should be equipped 
with a clean, hydrocarbon free two stage 
regulator and shut off valve. 
•  All external tubing, regulators, valves, 
pumps,  fittings, etc. are clean. 
•  The correct fuel type is being used. 
•  The THC content of the supply gases 
are compatible with the analysis range. 
•  The calibration background gases are 
similar to the sample. 
•  The purge air out, burner exhaust, and 
bypass are vented to atmospheric pres-
sure. The pressure should be constant. 
•  The burner exhaust tube must be 
slanted down a minimum of 6 degrees 
from horizontal. 
•  The bypass line connection must be 
slanted down a minimum of 6 degrees 
from horizontal for drainage of water 
condensation. 
•  If required, thermal insulation around the 
bypass fitting to prevent condensation in 
the bypass restrictor. 
•  If required, thermal insulation for the 
sample inlet connection to minimize the 
cold spot. 
•  The heated line is at the correct tem-
perature. 
•  The sample, zero, and span gases are 
at the correct temperature. 
•  The heated line to have over tempera-
ture protection. 
•  The sample, bypass, and burner ex-
haust tubing material must handle high 
temperature and have thermal insulation 
to protect from burns. 
•  The purge air out tubing to be 3/8 inch 
and less than 4 feet in length. 
•  All external gas connections have been 
leak checked. 
•  The dead volume for external sample 
and fuel lines have been minimized. 
•  The stainless steel tubing used for the 
fuel and sample lines is clean.