Maintenance Object Repair Procedures
Page 10-142
ASAI-PT
10
Level 1 Status Inquiry Test (#621)
This test determines the state of the transmission facility of a BRI port at the
Level 1 (L1) or physical layer. L1 can be in one of two possible states: Activated
or Deactivated.
Level 1 (L1) or physical layer. L1 can be in one of two possible states: Activated
or Deactivated.
The Activated state is the correct state for an ISDN-BRI port. In this state the
Level 1 interface can communicate with the BRI endpoint or ASAI adjunct
administered on this port. This test passes if the state of L1 is activated. This test
also passes if software has taken this port out of service.
Level 1 interface can communicate with the BRI endpoint or ASAI adjunct
administered on this port. This test passes if the state of L1 is activated. This test
also passes if software has taken this port out of service.
The Deactivated state indicates a problem with the ASAI circuit pack. When in
this state, the Level 1 interface is idle and is not trying to communicate with the
BRI endpoints or adjunct. When an ASAI port is placed in the out-of-service
state, Level 1 is also put into the deactivated state. This could be due either to
the system detecting a fault with the port or in response to a
this state, the Level 1 interface is idle and is not trying to communicate with the
BRI endpoints or adjunct. When an ASAI port is placed in the out-of-service
state, Level 1 is also put into the deactivated state. This could be due either to
the system detecting a fault with the port or in response to a
busyout port
PCSSpp
request.
FAIL
The Looparound test has failed.
1. If the test fails repeatedly, attempt to reset the circuit pack if the other
ports on the board are not in use. Reset the circuit pack by issuing the
busyout board PCSS
and the
reset board PCSS
commands.
2. If the test fails again, execute
test pkt P
on the management terminal. If
this fails, follow the failure procedures the in PKT-BUS section.
3. If the tests executed in Step 2 pass, the problem is local to the BRI
board. Replace the circuit pack.
PASS
The BRI Port Local LAN Looparound test has passed.
Table 10-47.
TEST #618 BRI Port Local LAN Looparound —
Continued
Error
Code
Code
Test
Result
Description/Recommendation