CHAPTER 3 Notes on Carrying In and Installing the Product 
3.1 Elevator Load Conditions 
34 
C122-H007-01EN 
 
  Notes on Carrying In and 
CHAPTER 3
Installing the Product 
This chapter provides notes on carrying in and installing the PRIMEQUEST 2000 series server. 
3.1 
Elevator Load Conditions 
The rack with the device mounted is wider than the average computer. Therefore, to use an elevator to carry 
in the rack, the rack may need the side boards or doors removed before loading on the elevator. When using 
an elevator to carry in the rack, see the elevator load conditions in 
 and 
confirm that you are properly loading the rack on the elevator. 
TABLE 3.1 Elevator load conditions 
Elevator 
code 
Load 
capacity 
[kg] 
Width 
(*1) 
Depth 
(*1) 
 
Height 
(*1) 
Width 
(*2) 
Height 
(*2) 
Rack 
Models 
2742/2737/2724/ 
2642/2624/2616 
Models 
1740/1640/1624 
P-6-C0 
450 
1400 
850 
2300 
800 
2100 
Cannot be loaded 
P-9-C0 
600 
1400 
1100 
2300 
800 
2100 
Cannot be loaded 
P-11-C0 
750 
1400 
1350 
2300 
800 
2100 
Can be loaded 
P-13-C0 
900 
1600 
1350 
2300 
900 
2100 
Can be loaded 
P-15-C0 
1000 
1600 
1800 
1500 
1300 
2300 
900 
1000 
2100 
Can be loaded 
P-17-C0 
1150 
1800 
2000 
1500 
1350 
2300 
1000 
1100 
2100 
Can be loaded 
P-20-C0 
1350 
1800 
2000 
1700 
1500 
2300 
1000 
1100 
2100 
Can be loaded 
P-24-C0 
1600 
2000 
2150 
1750 
1600 
2300 
1100 
2100 
Can be loaded 
*1 Interior dimensions of the cab [mm] 
*2 Door opening dimensions [mm] 
 
3.2 
Earthquake Preparedness Measures 
The purpose of the earthquake preparedness measures is to prevent the computer from falling and breaking, 
and to ensure operator safety as well as quick system recovery. To prevent damage to the computer system 
from an earthquake, Fujitsu provides an earthquake countermeasure called "fixed construction." (A fixed 
construction prevents the device from falling by fixing it in place.) 
The necessity of a fixed construction is determined from the following factors: 
Magnitude of floor vibrations at the installation site 
Whether the floor is a raised floor 
Device structure 
Before choosing an earthquake countermeasure and performing the actual work for earthquake 
preparedness, consult with Fujitsu's engineering works department.