Where will the UPS be installed?
What is the maximum transition time that your installation will allow?
NOTE
Extreme Networks recommends that you use a UPS that provides online protection. 
Calculating Amperage Requirements
To determine the size of UPS that you need, use the following procedure:
1
To find Volt-Amps (VA), locate the voltage and amperage requirements for each piece of equipment. 
These numbers are usually located on a sticker on the back or bottom of your equipment. Then 
multiply the numbers together to get VA: 
VA = Volts x Amperes 
2
Add the VA from each piece of equipment together to find the total VA requirement. 
To determine the minimum amperage requirements for your UPS, we recommend that you add 30% 
to the total.
UPS Transition Time
Transition time is the time that is necessary for the UPS to transfer from utility power to full-load 
battery power. For Extreme Networks products, a transition time of less than 20 milliseconds is 
required for optimum performance. 
Applicable Industry Standards
For more information, see the following ANSI/TIA/EIA standards:
ANSI/TIA/EIA-568-A—discusses the six subsystems of a structured cabling system.
ANSI/TIA/EIA-569-A—discusses design considerations.
ANSI/TIA/EIA-606—discusses cabling system administration.
ANSI/TIA/EIA-607—discusses commercial building grounding and bonding requirements.