© 2011 Cisco and/or its affiliates. All rights reserved. This document is Cisco Public Information. 
Page 30 of 36 
Figure 25.    Transaction per Minute Scaling After Adding Each Virtual Machine 
 
Scenario 3: SQL Server Consolidation Using Cisco UCS B440 M2 With 100 GB Database 
As described in workload section, we started test with one large database in the SQL Server Instance running on 
the virtual machine. We captured the test results at the end of test. Later we keep on adding one virtual machine at 
a  time  with  the  same  memory  and  database  instance.  At  every  virtual  machine  count  we  captured  metrics of  the 
workload. It was observed that the best utilization of CPU and Memory of each virtual machine as well as Physical 
machine was sustained until 7 virtual machines were deployed on the same physical machine. 
Figure 26 shows the resource Utilization of Cisco UCS B440 M2, especially CPU and memory of physical machine 
after  adding  each  virtual  machine  one  after  another  with  one  large  database  in  each  virtual  machine  and 
concurrently running OLTP workload one each virtual machine. Workload was capped to make sure that resources 
(Memory and CPU) were not saturated. In this testing process we observed 86 percent of memory utilization and 
74  percent  CPU  Utilization.  As  it  is  shown  in  the  graph,  physical  machine  still  had  enough  CPU  and  memory  to 
handle any unexpected spikes in the workloads.