There are many solutions to address cable management. They can range from
simple cable management rings, to cable management brackets, to vertical or
horizontal organizers, to troughs and ladders.
simple cable management rings, to cable management brackets, to vertical or
horizontal organizers, to troughs and ladders.
All SV Director Server cables should be properly dressed so as not to interfere
with each other or other pieces of equipment. Use local practices to ensure that
the cables attached to your appliance are properly dressed.
with each other or other pieces of equipment. Use local practices to ensure that
the cables attached to your appliance are properly dressed.
Method of Procedure
As described previously, part of your preparation includes reviewing installation
plans or MOPs. An example of a MOP (a pre-installation checklist of tasks and
considerations that need to be addressed and agreed upon before proceeding
with the installation) is as follows:
plans or MOPs. An example of a MOP (a pre-installation checklist of tasks and
considerations that need to be addressed and agreed upon before proceeding
with the installation) is as follows:
1. Assign personnel.
2. Determine protection requirements for personnel, equipment, and tools.
3. Evaluate potential hazards that may affect service.
4. Schedule time for installation.
5. Determine any space requirements.
6. Determine any power requirements.
7. Identify any required procedures or tests.
8. On an equipment plan, make a preliminary decision that locates each SV
Director Server that you plan to install.
9. Read this hardware installation guide.
10. Verify the list of replaceable parts for installation (screws, bolts, washers, and
so on) so that the parts are identified.
11. Check the required tools list to make sure the necessary tools and test
equipment are available. See Required Tools and Equipment.
12. Perform the installation.
Unpacking and Checking the Contents of Your Shipment
The shipping package for the SV Director Server is designed to reduce the
possibility of product damage associated with routine material handling
experienced during shipment. To reduce the potential damage to the product,
transport the unit in its original Cisco packaging. Failure to do so may result in
damage to the unit. Also, do not remove the unit from its shipping container until
you are ready to install it.
possibility of product damage associated with routine material handling
experienced during shipment. To reduce the potential damage to the product,
transport the unit in its original Cisco packaging. Failure to do so may result in
damage to the unit. Also, do not remove the unit from its shipping container until
you are ready to install it.
The server, cables, and any optional equipment you ordered may be shipped in
more than one container. When you unpack the containers, check the packing
list to ensure that you received all the parts listed in Table 10
more than one container. When you unpack the containers, check the packing
list to ensure that you received all the parts listed in Table 10
. A ―Notes‖ section
has been provided to record damaged or missing items.