Setup and Operation 
3-3 
Laser Link III Mainframe Initial Checkout 
Introduction 
Initial checkout provides a means of proving the operational readiness of the Laser 
Link III Mainframe. 
Important:  Perform this procedure immediately following the installation of the 
mainframe and prior to the installation of additional Laser Link components. 
Procedure 
The following procedure contains individual step-by-step instructions to perform 
the initial checkout.  Additional operational information is provided following the 
step-by-step instructions that may be useful as the unit remains in service over time.  
This procedure is valid for mainframes containing either the User Panel or the 
Element Management Interface Card (EMIC). 
Follow these steps to perform the initial checkout procedure. 
1. 
IF the mainframe… 
THEN… 
is equipped with a redundant power supply 
perform steps 2 and 3. 
is NOT equipped with a redundant power 
supply 
go to step 4. 
 
2. 
If a redundant power supply is connected to the mainframe, place the 
Redundant Power/“B” Alarm switch on the Status Monitoring module in the 
ON position or place the Redundant Power/“B” Alarm switch on the EMIC 
module in the forward position. 
 
 
 
3. 
Apply power to the mainframe.  On the Status Monitoring/EMIC module: 
• 
PWR A LED is lit green 
• 
PWR B LED is lit green 
• 
ALARM LED is extinguished