Telecell Installation Manual 
Commissioning 
TL-006175-PR Issue 5 © Telensa Ltd 2018 
 
 
  Page 26 
 
3.5.2 
Telecell Control 
To test if a Telecell can be controlled and return meaningful data, use the Polling and 
Override functions within the PLANet user interface. The sequence is as follows: 
1) 
Poll the Asset (for the power parameter) and record the reading, found within the 
Readings page – Readings > Lamp Electrical > Power. 
2) 
Override the Asset to Full On. 
3) 
Poll the Asset (for the power parameter) and record the reading, found within the 
Readings page. 
4) 
Include if the dimming unit is installed - Override the Asset to DIM2. 
5) 
Include if the dimming unit is installed - Poll the Asset (for the power parameter) 
and record the reading, found within the Readings page. 
6) 
Override the Asset to Return to Normal Operation. 
7) 
Poll the Asset (for the power parameter) and record the reading, found within the 
Readings page. Confirm that the readings obtained are as expected in 
accordance with the associated Lamp Type. 
Note:  The Properties section can also be used to carry out this task on single 
Assets if the User is familiar with this process. 
3.5.2.1 
Polling 
1) 
To Poll an Asset, navigate to the Polling page, select the Asset and Parameter 
to be polled and click the Poll Asset tab.  
The progress of this task can be viewed within the Tasks > Polling page.