Place the Receiver in the approximate location for final use.
⇒
The Receiver is mounted onto a standard single gang electrical box.
⇒
Connect the power supply and system network cables to the 5 pin connector on the Master
receiver (the 12VDC to 24 VDC supply should be OFF while connecting).
receiver (the 12VDC to 24 VDC supply should be OFF while connecting).
Note: Each Receiver has a unique electronic serial number that is associated with the location of
the Receiver in the building. The computer indicates the correct location of an event on the floor
the Receiver in the building. The computer indicates the correct location of an event on the floor
plans by using this serial number association. Therefore, ensure that the correct Receiver is
installed at the corresponding location.
⇒
If the wall is dielectric (plaster),
the antenna can be left parallel to
the antenna can be left parallel to
the wall, but should point away
from the receiver.
⇒
If the receiver is installed on a
conductive surface (metal wall, or wall
with metal mesh inside), the antenna
with metal mesh inside), the antenna
should be swiveled away from mounting