Utica Boilers MGB Series II/MGC Series 安装指导

下载
页码 28
5
1. 
Installation must conform to the requirements of the 
authority having jurisdiction or, in the absence of such 
requirements, to the National Fuel Gas Code, ANSI 
Z223.1/NFPA 54.
2. 
Where required by the authority having jurisdiction, the 
installation must conform to the Standard for Controls 
and Safety Devices for Automatically fired Boilers, 
ANSI/ASME CSD-1.
3. 
Boiler series is classified as a Category I.  Vent 
installation shall be in accordance with "Venting of 
Equipment ," of the National Fuel Gas Code, ANSI 
Z223.1/NFPA 54 or applicable provisions of the local 
building codes. 
4. 
Boiler has met safe lighting and other performance 
criteria with the gas manifold and control assembly on 
the boiler per the latest revision of ANSI Z21.13/CGA 
4.9.
5. 
Install boiler such that gas ignition system components 
are protected from water (dripping, spraying, rain, 
etc.) during appliance operation and service, (circulator 
replacement, condensate trap, control replacement, 
etc.).
6. 
Locate boiler on level, solid base as near chimney as 
possible and centrally located with respect to heat 
distribution system as practical.
7. 
Allow 24 inches (610mm ) at front and right side for 
servicing and cleaning. 
8. 
When installed in utility room, door should be wide 
enough to allow largest boiler part to enter, or to 
permit replacement of another appliance such as water 
heater.
WARNING
Fire hazard. Do not install boiler on combustible 
flooring or carpeting. Failure to follow these 
instructions could result in death or serious injury.
!
   
9. 
FOR INSTALLATION ON  NON-COMBUSTIBLE FLOORS 
ONLY - For installation on combustible flooring special 
base must be used. (See Repair Parts, Optional Kits 
Manual). Do not install boiler on carpeting. Minimum 
clearances to combustible construction are:
TOP ....................................18 IN. (457mm)
FRONT .........................................ALCOVE *
FLUE CONNECTOR ................. 6 IN. (152mm)
REAR ................................... 4 IN. (102mm)
CONTROL SIDE ..................... 9 IN. (229mm)
OTHER SIDE ........................... 3 IN. (76mm)
HOT WATER PIPING ................ Per Local Code
NOTE: Greater clearances for access should supersede fire 
protection clearances.
* Definition of Alcove is three sided space with no wall in 
front of boiler. ANSI standard for alcove is 18 inches from 
front of appliance to leading edge of side walls as shown 
below.
Minimum Clearances to Combustible 
Construction (as seen from above)
2 - INSTALLATION PROCEDURE
WARNING
Improper installation, adjustment, alteration, service 
or maintenance could result in death or serious 
injury
.
!
   
3"
4"
BOILER
18"
9"
Front