Figure 31 shows end section and provided tappings. 
Tappings are same in both right and left end sections.
 
OPENING
SIZE
STEAM
A
4”
Supply and Return
B
½”
Primary LWCO and Gauge 
Glass Set
C
¾”
Drain, Left End
C
¾”
Drain, Right End
D
½”
Plugged
E
1”
Accessories
*F
1”
Safety Valve
G
¾”
Plugged or Electronic (Probe 
Type) LWCO
*If using opening F for other than Safety Valve 
or Safety Relief Valve, or  Safety/Relief valve 
is larger than 1”, Install Safety/Relief Valve in 
Header Piping as near boiler as possible.
A
B
A
B
C
D
E
F
G
BOILER TRIM
Following controls are supplied as standard 
equipment.  Details of their function and operation 
will be found in section on Checking and Adjustments 
page 33.
STEAM TRIM
1. 
Low Water Cut-Off (mounted externally) with blow-off 
valve
2. 
High Pressure Limit Control
3. 
Pressure Gauge
4. 
Water Gauge Glass Set
5. 
Siphon Loop
6. 
Safety Valve 15 psi. See page 27 for installation location.
STEAM TRIM ASSEMBLY
Field assemble Steam Trim, Low Water Cut-Off, High 
Pressure Limit Control, Pressure Gauge, Water Gauge 
Glass Set and Siphon Loop, as shown in Figure 32.  
See Figure 31 and Chart above for location of 
controls.
WATER LEVEL 
29” TO FLOOR
TAPPINGS
Figure 31
Figure 32
NOTICE
Do not place any shutoff between pressure relief 
valve and boiler, or on discharge pipes between 
such safety valves and atmosphere. Installation of 
pressure relief valve shall conform to requirements 
of ANSI/ASME Boiler and Pressure Vessel Code, 
Section IV.
Field Assembled