Siemens Network Hardware D410 用户手册
D410
Commissioning Manual, 08/2008 Edition
Commissioning Manual, 08/2008 Edition
61
Commissioning (software)
4
4.1
Overview of commissioning
Prerequisites
Prerequisites for commissioning the SIMOTION D410:
● The system has been connected and wired.
● The SIMOTION D410 is switched on and started up (STOP state).
● SIMOTION SCOUT (with integrated STARTER) has been installed and started on the
● The system has been connected and wired.
● The SIMOTION D410 is switched on and started up (STOP state).
● SIMOTION SCOUT (with integrated STARTER) has been installed and started on the
programming device / PC.
● Communication between the SIMOTION D410 and the programming device / PC is
configured.
● You have created a project and installed a SIMOTION D410 in the project.
NOTICE
For the SIMOTION D410, a reset of the drive must not be set using the expert list of the
control unit in the p972 parameter (drive unit reset). This causes SIMOTION D410
malfunction, the RDY, RUN/STOP and SF/BF LEDs glow red. In this fault situation, the
SIMOTION D410 must be switched off and on again.
Commissioning steps
This chapter describes the steps in configuring the plant and testing the configured stand-
alone drive and axis. The steps in commissioning are listed below in the order as
recommended:
1. Configuring SINAMICS Integrated
1. Configuring SINAMICS Integrated
The integrated drive SINAMICS Integrated can be configured in offline or online mode:
– Offline configuration
– Offline configuration
All components and their order number must be known for the offline configuration.
– Online configuration
The configuration in online mode allows you to upload all information of the connected
DRIVE-CLiQ components to your user project.